HomeMy WebLinkAboutContract 1073-2 Edom Hill Transfer Station City Mitigation Agreement
Amendment No. 2
The City of Cathedral City (herein called "CITY") and the County of Riverside (herein called
"COUNTY") previously entered into an agreement on November 5, 2002, which was
subsequently amended April 21, 2009, to resolve matters related to issues surrounding the Edom
Hill Transfer Station and related improvements (herein called "Project").
WHEREAS, on August 13, 2002, COUNTY, as the lead agency, adopted an Initial
Study/Mitigated Negative Declaration (IS/MND) (SCH No. 2002051067) for the development of
the Edom Hill Transfer Station; and
WHEREAS,the Edom Hill Transfer Station became operational on December 1, 2004; and
WHEREAS, CITY agreed to construct certain improvements within specified timeframes; and
WHEREAS, the agreement was amended April 21, 2009 due to a reduction in tonnage at the site
resulting from the economic downturn; and
WHEREAS, CITY will receive significant ongoing revenue during the life of the Project after
improvements are complete that will exceed total improvement costs; and
WHEREAS, IS/MND (SCH No. 2002051067) identified that in 2014, the transfer station was
projected to reach build-out (2,600 tons/day); as such, Mitigation Measure T-2 required traffic
signals at the intersections of Edom Hill Road/Varner Road, and Date Palm Drive/Varner Road;
and
WHEREAS, COUNTY recognizes that in 2014, tonnage delivered to the Edom Hill Transfer
Station was significantly lower than the projected 2,600 tons per day (avg. of 1,150 tpd);
therefore, the traffic conditions requiring installation of traffic signals were not met; and
WHEREAS, CITY agrees to maintain the requirement to install traffic signals at the
intersections identified in Mitigation Measure T-2; however, the timing of such improvements
shall be based upon tonnage delivered to the Edom Hill Transfer Station, not date specific
(December 2014): and
WHEREAS, COUNTY recognizes that the reduction in tonnage has affected the timing of the
improvements in the amended agreement; and
JUL 1 2 2016 l Z
WHEREAS, COUNTY recognizes that CITY has completed the following improvements:
1) Construction of traffic turn lane pockets including asphalt overlays of entire roadway,
at the following locations:
a. On southbound Varner Road, onto Date Palm Drive
b. On southbound Varner Road, onto Edom Hill Road
c. On northbound Varner Road, onto Edom Hill Road
2) Repair/reconstruction of short reaches of structurally damaged roadway along Edom
Hill Road
3) Overlay of the entire existing Edom Hill Road with 1.5" asphalt from the East Project
boundary to Varner Road, with reconstruction as needed near its intersection with
Varner Road
NOW,THEREFORE, THE PARTIES AGREE AS FOLLOWS:
CITY shall:
1. Construct the remaining project related road improvements listed below, on or before the
following revised schedule:
a. No later than twelve months after tonnage received at the facility consistently
reaches 2,500 tons per day:
1) Signalize the Date Palm Drive and Varner Road Intersection, and
2) Signalize the Edom Hill Road and Varner Road Intersection.
b. No later than twelve months after tonnage received at the facility consistently
reaches 3,500 tons per day:
1) Construct an approximate 4,700 foot climbing Lane along Edom Hill
Road, from Varner Road easterly.
/
PD#68802viI 2
Except as specifically modified or amended above, all of the terms, covenants and conditions of
said agreement of the 5th of November 2002 and Amendment No. 1, shall remain in full force
and effect between the parties hereto.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 2 to Agreement
to be duly executed on May 2 5, 2 016 ,
RIVERSIDE COUNTY CITY OF CATHEDRAL CITY
DEPARTMENT OF WASTE RESOURCES 68-700 Avenida Lalo Guerrero
14310 Frederick Street Cathedral City, CA 92234
Moreno Valley, CA 92553
Dated: �`/ Dated: May 25. 2 0 _..
-
RECOMMEND D FOR APPRO L By: �.
Stan enry, Mayor
By:
Hans Kernkamp,General Ma -Chief Engineer ATTEST:
CO AS F ' ' . .DE By:
l _
jo,
C...441 i .
Cler (Seal)
By: jr1. A. /..
or airman :oard o Supervisors All
J. BENOIT
JOHN B Ilif. • ' iltt--/--&-La----
ATTEST: Charles McClendon, Ci Manager
Iti !..1.• A I ,ffaik.-40.1 ,4 °l'A -'1Vdf ,r
e of the :.. ;. t
By: sem.
Seat Cit 'Attorney
. )krt, a PP: '1E G N., t„0", - >
1k
r
KiPNlS DA E
PD#68802v 11 3
Edom Hill Transfer Station City Mitigation Agreement
Amendment No. 2
The City of Cathedral City (herein called "CITY") and the County of Riverside (herein called
"COUNTY") previously entered into an agreement on November 5, 2002, which was
subsequently amended April 21, 2009, to resolve matters related to issues surrounding the Edom
Hill Transfer Station and related improvements (herein called "Project").
WHEREAS, on August 13, 2002, COUNTY, as the lead agency, adopted an Initial
Study/Mitigated Negative Declaration (IS/MND) (SCH No. 2002051067) for the development of
the Edom Hill Transfer Station; and
WHEREAS, the Edom Hill Transfer Station became operational on December 1, 2004; and
WHEREAS, CITY agreed to construct certain improvements within specified timeframes; and
WHEREAS, the agreement was amended April 21, 2009 due to a reduction in tonnage at the site
resulting from the economic downturn; and
WHEREAS, CITY will receive significant ongoing revenue during the life of the Project after
improvements are complete that will exceed total improvement costs; and
WHEREAS, IS/MND (SCH No. 2002051067) identified that in 2014, the transfer station was
projected to reach build-out (2,600 tons/day); as such, Mitigation Measure T-2 required traffic
signals at the intersections of Edom Hill RoadNarner Road, and Date Palm DriveNarner Road;
and
WHEREAS, COUNTY recognizes that in 2014, tonnage delivered to the Edom Hill Transfer
Station was significantly lower than the projected 2,600 tons per day (avg. of 1,150 tpd);
therefore, the traffic conditions requiring installation of traffic signals were not met; and
WHEREAS, CITY agrees to maintain the requirement to install traffic signals at the
intersections identified in Mitigation Measure T-2; however, the timing of such improvements
shall be based upon tonnage delivered to the Edom Hill Transfer Station, not date specific
(December 2014): and
WHEREAS, COUNTY recognizes that the reduction in tonnage has affected the timing of the
improvements in the amended agreement; and
JUL 1 2 2016 I Z c—
WHEREAS, COUNTY recognizes that CITY has completed the following improvements:
1) Construction of traffic turn lane pockets including asphalt overlays of entire roadway,
at the following locations:
a. On southbound Varner Road, onto Date Palm Drive
b. On southbound Varner Road, onto Edom Hill Road
c. On northbound Varner Road, onto Edom Hill Road
2) Repair/reconstruction of short reaches of structurally damaged roadway along Edom
Hill Road
3) Overlay of the entire existing Edom Hill Road with 1.5" asphalt from the East Project
boundary to Varner Road, with reconstruction as needed near its intersection with
Varner Road
NOW, THEREFORE,THE PARTIES AGREE AS FOLLOWS:
CITY shall:
1. Construct the remaining project related road improvements listed below, on or before the
following revised schedule:
a. No later than twelve months after tonnage received at the facility consistently
reaches 2,500 tons per day:
1) Signalize the Date Palm Drive and Varner Road Intersection, and
2) Signalize the Edom Hill Road and Varner Road Intersection.
b. No later than twelve months after tonnage received at the facility consistently
reaches 3,500 tons per day:
1) Construct an approximate 4,700 foot climbing Lane along Edom Hill
Road, from Varner Road easterly.
I
PD#68802v11 2
modified or amended above, all of the terms, covenants and conditions of
Except as specifically
said agreement of the 5th of November 2002 and Amendment No. I, shall remain in full force
and effect between the parties hereto.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 2 to Agreement
to be duly executed on May 2 5, 2 016
RIVERSIDE COUNTY CITY OF CATHEDRAL CITY
DEPARTMENT OF WASTE RESOURCES 68-700 Avenida Lalo Guerrero
14310 Frederick Street Cathedral City, CA 92234
Moreno Valley, CAA 92553
Dated: 6/f/c Dated: May 2 5. 2 0
RECOMMEND/ / D FOR APPRO By: j„?/>►r!:111ff
Stan enry, Mayor
By:
Hans Kernkamp,General M -Chief Engineer ATTEST:
Z,f G
CO •' j
F ' ' - .DE By: 7P4
Cler, (Seal)
By.: ',iip, i..
�
� airman/s oard o Supervisors �Il- ILEPK_La-_�
JOHN J. BENOIT B rr
ATTEST: Charles McClendon, Ci Manager
1/. !, ,_. A A ,./.....A OA ,1 0 t ..-s, Aloe
e of the : •. • By: ji. sv
(Seal) Cit 'Attorney
i'H a �'R �.�E GG. NVCOUN "; , l
kV �
. F.4: P KIPNIS DA_E
PD#68802v11 3