HomeMy WebLinkAboutCC Reso 2021-07 RESOLUTION NO. 2021- 07
RESOLUTION ADOPTING A LIST OF PROJECTS FOR
FISCAL YEAR 2021-22 FUNDED BY SB 1: THE ROAD
REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the
Governor in April 2017 to address the significant multi-modal transportation funding
shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will
ensure the residents of Cathedral City ("CITY") are aware of the projects proposed for
funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the CITY must adopt by resolution a list of projects proposed to
receive fiscal year funding from the Road Maintenance and Rehabilitation Account
(RMRA), created by SB 1, which must include a description and the location of each
proposed project, a proposed schedule for the project's completion, and the estimated
useful life of the improvement; and
WHEREAS, the CITY, will receive an estimated $900,000.00 in RMRA funding in
Fiscal Year 2021-2022 from SB 1; and
WHEREAS, this is the fifth year in which the City is receiving SB 1 funding and will
enable the City to continue essential road maintenance and rehabilitation projects, safety
improvements, repairing and replacing aging bridges, and increasing access and mobility
options for the traveling public that would not have otherwise been possible without SB
1; and
WHEREAS, the CITY has undergone a robust public process to ensure public
input into our community's transportation priorities/the project list; and
WHEREAS, the CITY used a Pavement Management System to develop the SB
1 project list to ensure revenues are being used on the most high-priority and cost-
effective projects that also meet the community's priorities for transportation investment;
and
WHEREAS, the funding from SB 1 will help the CITY maintain and rehabilitate
streets throughout the CITY this year and in the future; and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs
Assessment found that the CITY's streets and roads are in a poor condition and this
revenue will help us increase the overall quality of our road system and over the next
decade will bring our streets and roads into a "good condition" condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and
roads infrastructure with a focus on basic maintenance and safety, investing in complete
ten (10) streets infrastructure, and using cutting-edge technology, materials and
practices, will have significant positive co-benefits statewide.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City
Council of the City of Cathedral City, State of California, as follows:
1. The foregoing recitals are true and correct.
2. The following proposed project will be funded in-part or solely with fiscal year 2021-
2022 Road Maintenance and Rehabilitation Account revenues:
Proposed Project 1: Whispering Palms Neighborhood Street Pavement
Rehabilitation.
Description: The proposed Project consists of five residential streets requiring
asphalt reconstruction.
Location: Candlewood Drive, Shifting Sands Trail, Whispering Palms Trail,
Sky Blue Water Trail, Navajo Trail, Pueblo Trail, and Mission Indian Trail
between Ramon Road and Avenue 33.
Estimated Useful Life: Twenty (20) years
Project Start: Spring 2021
Project Completion: Spring 2021
Estimated Cost: $1,000,000.00
Proposed Project 2: Landau Boulevard and McCallum Way Intersection Traffic
Signal Construction
Description: The proposed project will provide a signalized intersection on
Landau Boulevard and McCallum Way near Mt. San Jacinto High School. The
intersection has a high volume of pedestrian traffic from students. In 2015, this
intersection was also the location of a pedestrian fatality.
Location: Traffic intersection of Landau Boulevard and McCallum Way.
Estimated Useful Life: Twenty (20) years
Project Start: Fall 2021
Project Completion: Summer 2022
Estimated Cost: $400,000.00
3. The following previously proposed and adopted project may utilize fiscal year
2021-22 Road Maintenance and Rehabilitation Account revenues in its delivery.
With the relisting of this project in the adopted fiscal year resolution, the City is
reaffirming to the public and the State our intent to fund this project with Road
Maintenance and Rehabilitation Account revenues:
Proposed Project 3: Century Park Neighborhood Street Pavement Rehabilitation
Description: The Century Park Neighborhood includes rehabilitation and/or
reconditioning of various residential streets within the Century Park Neighborhood
area.
Location: The Century Park Neighborhood is bound between Avenue 30 to the
north, McCallum Way to the south, Date Palm Drive to the west, and Da Vall Drive
to the east.
Estimated Useful Life: Twenty (20) years
Project Start: Spring 2022
Project Completion: Summer 2022
Estimated Cost: $1,400,000.00
PASSED AND ADOPTED by the City Council of the City of Cathedral City, State
of California this 12th day of May 2021, by the following vote:
Ayes: Councilmembers Ross, Lamb and Carnevale; Mayor Pro Tem Gutierrez
and Mayor Gregory
Noes: None
Absent: None
Abstain: None